Wind Damage >> Recovering Hurricane Katrina

Attachment of Brick Veneer in High-Wind Regions Hurricane Katrina Recovery Advisory FEMA December 2005 Purpose: To recommend practices for installing brick veneer that will enhance wind resistance in high-wind areas. Key Issues. Brick veneer is frequently blown off Recovering Hurricane Katrina walls of residential and commercial buildings (Figure 1). 

When brick veneer fails, wind-driven water can enter and damage buildings, and building occupants can be vulnerable to injury from windborne debris (particularly if walls are sheathed with plastic foam insulation or Recovering Hurricane Katrina wood fiberboard in lieu of wood panels). Pedestrians in the vicinity of damaged walls can also be vulnerable to injury from falling veneer (Figure 2). 

Figure 1. Failed brick veneer. Plastic foam wall sheathing was Recovering Hurricane Katrina installed over the wood studs (plywood was temporarily installed after the brick failure). Figure 2. The upper portion of the brick veneer at this apartment building collapsed. 

Pedestrian and vehicular traffic in the vicinity of the damaged wall were vulnerable to injury and Recovering Hurricane Katrina damage if remaining portions of the wall were to collapse during subsequent storms. 

Common failure modes include tie (anchor) fastener pull-out (Figure 3), failure of masons to embed ties into the mortar (Figure 4), poor bonding between ties and Recovering Hurricane Katrina mortar and mortar of poor quality (Figure 5), and tie corrosion (Figure 6). Figure 3. This tie remained embedded in the mortar joint while the smooth-shank nail pulled from the stud. 

These four ties were never embedded into the mortar joint. Figure 5. This tie was embedded in the mortar, but the bond was poor. Figure 6. There were several ties in this portion of the wall, Recovering Hurricane Katrina but they failed due to severe corrosion. Ties are often installed before brick laying begins. When this is done, ties are often improperly placed above or below the mortar joints. 

When misaligned, the ties must be angled up or down in order for the ties to be embedded into the mortar joints (Figure 7). Misalignment not only reduces embedment depth but also reduces the effectiveness of the ties because Recovering Hurricane Katrina wind forces do not act parallel to the ties themselves. Figure 7. Misalignment of the tie reduces the embedment and promotes veneer failure. 

Corrugated ties typically used in residential veneer construction provide little resistance to compressive loads. Use of compression struts would likely be beneficial, Recovering Hurricane Katrina but off-the-shelf devices do not currently exist. Two-piece adjustable ties (Figure 8) provide significantly greater compressive strength than corrugated ties. 

Figure 8. Examples of two-piece adjustable ties, one showing base and vee anchor and the other showing eye and Recovering Hurricane Katrina pintle anchor Many buildings that exhibited damaged veneer were not in compliance with current building codes. Building code requirements for brick veneer have changed over the years. 

Model codes prior to 1995 permitted brick veneer in any location, Recovering Hurricane Katrina with no wind speed restrictions. Wall area per tie in some model codes was greater than the current maximum. 

The current masonry code referenced in model building codes, Building Code Requirements for Masonry Structures, ACI 530/ASCE 5/TMS 402 (ACI 530) addresses brick veneer in two manners: Recovering Hurricane Katrina rational design and prescriptive requirements. Essentially all brick veneer in residential and low-rise construction follows the prescriptive requirements. 

The first edition of American Concrete Institute’s (ACI’s) 530 limited the use of prescriptive design to areas with a basic wind speed of 110 mph or less. The 2005 edition of ACI 530 extended the prescriptive requirements to include a basic wind speed of 130 mph, Recovering Hurricane Katrina with lower area per tie limits. 

In locations with a basic wind speed above 130 mph, the rational design approach must be used. Compliance with ACI 530-05 should reduce wind damage. The following Brick Industry Association (BIA) Technical Notes Recovering Hurricane Katrina provide guidance on brick veneer: Technical Notes 28 – Anchored Brick Veneer, Wood Frame Construction, Technical Notes.

Brick Veneer/Steel Stud Walls, and Technical Notes 44B – Wall Ties (available online at www.bia.org). These Technical Notes provide attachment recommendations, Recovering Hurricane Katrina but the recommendations are not specific for high-wind regions and are, therefore, inadequate. Construction Guidance The brick veneer wall system is complex in its behavior. 

There are limited test data on which to draw. The following guidance is based on professional judgment, wind loads specified in ASCE 7-02 "Design Loads for Buildings and Recovering Hurricane Katrina Other Structures,” fastener strengths specified in the American Forest and Paper Association’s (AF&PA’s) National Design Specification for Wood Construction, and brick veneer standards contained in ACI 530-05. 

In addition to the general guidance given in BIA Technical Notes 28 and 28B, the following are recommended: Note: In areas that are also susceptible to high seismic loads, brick veneer should be evaluated by an engineer to ensure it can resist seismic and Recovering Hurricane Katrina wind design loads. Stud Spacing: For new construction, space studs 16" on center, so that ties can be anchored at this spacing. 

Tie Fasteners: Ring-shank nails are recommended in lieu of smooth-shank nails. A minimum embedment of 2" is suggested. Ties: For use with wood studs: two-piece adjustable ties are recommended. However, Recovering Hurricane Katrina where corrugated steel ties are used, use 22-gauge minimum, 7/8" wide by 6" long, complying with ASTM A 366 with a zinc coating complying with ASTM.

A 153 Class B2. For ties for use with steel studs, see BIA "Technical Notes 28B – Brick Veneer/Steel Stud Walls.” Stainless steel ties should be used in areas within 3,000 feet of the coast. Tie Installation Install ties as the brick is laid so that the ties are properly aligned with Recovering Hurricane Katrina the mortar joints. Install brick ties spaced per Table 1. 

Studs should be installed at 16" spacing. Veneer tie locations for 24" stud spacing are included for repairing damaged veneer on existing buildings with the wider stud spacing. Locate ties within 8" of door and Recovering Hurricane Katrina window openings and within 12" of the top of veneer sections. Bend the ties at a 90-degree angle at the nail head in order to minimize tie flexing when the ties are loaded in tension or compression (Figure 9). Figure 9. 

Bend ties at nail heads Embed ties in joints so that mortar completely encapsulates the ties. Embed a minimum of 1.5" into the bed joint, Recovering Hurricane Katrina with a minimum mortar cover of 5/8" to the outside face of the wall (Figure 10). Figure 10. Tie embedment [Begin table]

How To Do Flood Remediation

Disease Risks and Sewage Exposure Flood water often contains raw sewage. Raw sewage can contain certain germs such as bacteria, viruses, and parasites. The risk of illness depends on how you were exposed to the flood water or sewage and how long you were exposed. The most common mode of infection i  read more..

Odor Control

Say Tenant Move Out Cleanup Odor Control out and did not inform you and it's been a couple of weeks. In that time animals of moved in and started living in your rental. How do you get them out of the walls and attic now that they've taken up residence there. Call a professional restoration company dealing with animal remova  read more..

How To Remove Ice Storm Damage Debris In An Emerge

A monitor (usually located in a monitoring observation tower at the debris management site) assesses what percentage of the truck's volume is full of debris. This percentage is then multiplied by the truck's declared maximum volume (as previously certified and announced on a placard on the side of t  read more..

How To Kill Mold After A Flood

Local codes generally require a building permit before yourepair or loodproof your structure. Usually you need toget a permit for electrical work, plumbing and repairs forstructural damage, such as foundations and Flood Damage How To Kill Mold After A Flood exterior walls.

Because your property may be located in a designat  read more..

How To Disinfect After Sewer Problems In A Basemen

It will probably never happen at your home, but in case it does, it's important to have the facts in advance. Remember, if you experience a sewer line blockage, Sewage Cleanup How To Disinfect After Sewer Problems In A Basemen call us first. This could save the unnecessary expense of a plumber. IF AN OVERFLOW OCCURS 1. Discontinue inside water use.2  read more..

How To Make Children Aware Of Disaster Management

    Cut plywood to fit over the window and dooropenings, flush with outside of the molding.Note: For buildings with metal door andwindow frames the alternative is tocut the plywood and 2x4s to fit theinside of the door frame buffed upagainst the band molding.2. Cut the 2x4s to fi  read more..

OSHA Requirements For Crime Scene Cleanup

Fourth, the fact that nursing homes are subject to infection control requirements imposed by the Health Care Financing Administration (HCFA) of the U.S. Department of Health and Human Services under the Medicare and Crime Scene Cleanup OSHA Requirements For Crime Scene Cleanup Medicaid programs and to infection control requirements of states doe  read more..

Ice Storm Cleanup

Debris removal supervision strategy help cities prepare for natural disaster related Debris Removal Ice Storm Cleanup and finally enhance the recovery procedure. To be operative, however, these strategies need to recognize crucial elements of the debris removal procedure, including the prequalification of debris removal   read more..

Flood Damage Restoration For Electronics

The second observation is that the first breakdown for the tantalum polymer capacitors occurs at 1.75 times rated voltage. This is roughly twice as high as the lowest voltage seen for the MnO2-based capacitors.While the precise numerical value of this advantage varies somewhat with manufacturer and   read more..

Dehumidification

Whether it is on a concrete slab or on piers, check to see that the building’s structure has not shifted on its foundation. Flood damaged wooden floors, if they do not warp or buckle, will sometimes push the walls outward at the base. Check for cracks in your masonry. Look near the  read more..