Wind Damage >> Recovering Hurricane Katrina

Attachment of Brick Veneer in High-Wind Regions Hurricane Katrina Recovery Advisory FEMA December 2005 Purpose: To recommend practices for installing brick veneer that will enhance wind resistance in high-wind areas. Key Issues. Brick veneer is frequently blown off Recovering Hurricane Katrina walls of residential and commercial buildings (Figure 1). 

When brick veneer fails, wind-driven water can enter and damage buildings, and building occupants can be vulnerable to injury from windborne debris (particularly if walls are sheathed with plastic foam insulation or Recovering Hurricane Katrina wood fiberboard in lieu of wood panels). Pedestrians in the vicinity of damaged walls can also be vulnerable to injury from falling veneer (Figure 2). 

Figure 1. Failed brick veneer. Plastic foam wall sheathing was Recovering Hurricane Katrina installed over the wood studs (plywood was temporarily installed after the brick failure). Figure 2. The upper portion of the brick veneer at this apartment building collapsed. 

Pedestrian and vehicular traffic in the vicinity of the damaged wall were vulnerable to injury and Recovering Hurricane Katrina damage if remaining portions of the wall were to collapse during subsequent storms. 

Common failure modes include tie (anchor) fastener pull-out (Figure 3), failure of masons to embed ties into the mortar (Figure 4), poor bonding between ties and Recovering Hurricane Katrina mortar and mortar of poor quality (Figure 5), and tie corrosion (Figure 6). Figure 3. This tie remained embedded in the mortar joint while the smooth-shank nail pulled from the stud. 

These four ties were never embedded into the mortar joint. Figure 5. This tie was embedded in the mortar, but the bond was poor. Figure 6. There were several ties in this portion of the wall, Recovering Hurricane Katrina but they failed due to severe corrosion. Ties are often installed before brick laying begins. When this is done, ties are often improperly placed above or below the mortar joints. 

When misaligned, the ties must be angled up or down in order for the ties to be embedded into the mortar joints (Figure 7). Misalignment not only reduces embedment depth but also reduces the effectiveness of the ties because Recovering Hurricane Katrina wind forces do not act parallel to the ties themselves. Figure 7. Misalignment of the tie reduces the embedment and promotes veneer failure. 

Corrugated ties typically used in residential veneer construction provide little resistance to compressive loads. Use of compression struts would likely be beneficial, Recovering Hurricane Katrina but off-the-shelf devices do not currently exist. Two-piece adjustable ties (Figure 8) provide significantly greater compressive strength than corrugated ties. 

Figure 8. Examples of two-piece adjustable ties, one showing base and vee anchor and the other showing eye and Recovering Hurricane Katrina pintle anchor Many buildings that exhibited damaged veneer were not in compliance with current building codes. Building code requirements for brick veneer have changed over the years. 

Model codes prior to 1995 permitted brick veneer in any location, Recovering Hurricane Katrina with no wind speed restrictions. Wall area per tie in some model codes was greater than the current maximum. 

The current masonry code referenced in model building codes, Building Code Requirements for Masonry Structures, ACI 530/ASCE 5/TMS 402 (ACI 530) addresses brick veneer in two manners: Recovering Hurricane Katrina rational design and prescriptive requirements. Essentially all brick veneer in residential and low-rise construction follows the prescriptive requirements. 

The first edition of American Concrete Institute’s (ACI’s) 530 limited the use of prescriptive design to areas with a basic wind speed of 110 mph or less. The 2005 edition of ACI 530 extended the prescriptive requirements to include a basic wind speed of 130 mph, Recovering Hurricane Katrina with lower area per tie limits. 

In locations with a basic wind speed above 130 mph, the rational design approach must be used. Compliance with ACI 530-05 should reduce wind damage. The following Brick Industry Association (BIA) Technical Notes Recovering Hurricane Katrina provide guidance on brick veneer: Technical Notes 28 – Anchored Brick Veneer, Wood Frame Construction, Technical Notes.

Brick Veneer/Steel Stud Walls, and Technical Notes 44B – Wall Ties (available online at www.bia.org). These Technical Notes provide attachment recommendations, Recovering Hurricane Katrina but the recommendations are not specific for high-wind regions and are, therefore, inadequate. Construction Guidance The brick veneer wall system is complex in its behavior. 

There are limited test data on which to draw. The following guidance is based on professional judgment, wind loads specified in ASCE 7-02 "Design Loads for Buildings and Recovering Hurricane Katrina Other Structures,” fastener strengths specified in the American Forest and Paper Association’s (AF&PA’s) National Design Specification for Wood Construction, and brick veneer standards contained in ACI 530-05. 

In addition to the general guidance given in BIA Technical Notes 28 and 28B, the following are recommended: Note: In areas that are also susceptible to high seismic loads, brick veneer should be evaluated by an engineer to ensure it can resist seismic and Recovering Hurricane Katrina wind design loads. Stud Spacing: For new construction, space studs 16" on center, so that ties can be anchored at this spacing. 

Tie Fasteners: Ring-shank nails are recommended in lieu of smooth-shank nails. A minimum embedment of 2" is suggested. Ties: For use with wood studs: two-piece adjustable ties are recommended. However, Recovering Hurricane Katrina where corrugated steel ties are used, use 22-gauge minimum, 7/8" wide by 6" long, complying with ASTM A 366 with a zinc coating complying with ASTM.

A 153 Class B2. For ties for use with steel studs, see BIA "Technical Notes 28B – Brick Veneer/Steel Stud Walls.” Stainless steel ties should be used in areas within 3,000 feet of the coast. Tie Installation Install ties as the brick is laid so that the ties are properly aligned with Recovering Hurricane Katrina the mortar joints. Install brick ties spaced per Table 1. 

Studs should be installed at 16" spacing. Veneer tie locations for 24" stud spacing are included for repairing damaged veneer on existing buildings with the wider stud spacing. Locate ties within 8" of door and Recovering Hurricane Katrina window openings and within 12" of the top of veneer sections. Bend the ties at a 90-degree angle at the nail head in order to minimize tie flexing when the ties are loaded in tension or compression (Figure 9). Figure 9. 

Bend ties at nail heads Embed ties in joints so that mortar completely encapsulates the ties. Embed a minimum of 1.5" into the bed joint, Recovering Hurricane Katrina with a minimum mortar cover of 5/8" to the outside face of the wall (Figure 10). Figure 10. Tie embedment [Begin table]

Sewage And Floodwaters Contains Bacteria

Sewage and floodwaters contains bacteria, fecal material, viruses and other hazardous microorganisms, which can cause disease. These "germs" can be transmitted by touching contaminated items or by tracking them into uncontaminated areas on shoes. Children and pets are especially vulnerable. Odors fr  read more..

Radon Mitigation

Why is radon the public health risk that it is? EPA estimates that about 20,000 lung cancer deaths each year in the U.S. are radon -related. Exposure to radon is the second leading cause of lung cancer after smoking. Radon Mitigation Radon Mitigation is an odorless, tasteless and invisible gas produced by the decay of natural  read more..

Emergency Board Up_Boarding Up Windows Can Prevent

Any building which has been made to conform to the provisions of this regulation during vacancy may be reoccupied under its original use and occupancy classification, provided that any systems which were disconnected or shut down during the period of vacancy are restored Emergency Board up Emergency Board Up_Boarding Up Windows Can Prevent to fully func  read more..

How To Make Children Aware Of Disaster Management

    Cut plywood to fit over the window and dooropenings, flush with outside of the molding.Note: For buildings with metal door andwindow frames the alternative is tocut the plywood and 2x4s to fit theinside of the door frame buffed upagainst the band molding.2. Cut the 2x4s to fi  read more..

Debris Removal

In this first step, a person needs to consider the likelihood of earthquake existence, extent of the earthquake, the likelihood of fire start after the earthquake and the extent of the ignited Smoke Damage Debris Removal. An earthquake is a natural danger and which might be examined by the statistics-based method.   read more..

Emergency Window Board Up

The following procedures and guidelines have been developed by the Division of Capital Asset Management and Maintenance (DCAM) to assist other State Agencies (Agency) with their responsibility to properly secure buildings and structures that they no longer occupy. It is the responsibility of the Age  read more..

How To Remove Flood Damage Debris In An Emergency

Debris estimating, assessing the total volume of debris that has to be dealt with before it is actually collected, is an art and science that is still developing. Results have been mixed, however. Officials in one county said while they had received an estimate of 100 tons of vegetative de  read more..

Floods

Is there any way to obtain a community-wide discount on the cost of flood insurance premiums? All communities in the NFIP adopt and enforce minimum standards for managing construction and development in their Special flood Hazard Areas. Some communities want to achieve a higher level of Flood Damage Floods&nb  read more..

How To Clean Up After Sewage Backups

Occasionally a blockage in a sewer line will result in a backup of sanitary sewage into a private home. If you experience a backup, immediately contact your city's public works department. The following information will answer the basic questions about what to do if you experience a backup and   read more..

Lead Paint Poisoning In Children

Physical examination should emphasize the neurological, gastrointestinal, and cardiovascular systems. The worker's weight and blood pressure should be recorded and the oral mucosa checked for pigmentation characteristic of a possible Burtonian or lead line on the gingiva.It should be noted, however,  read more..