Wind Damage >> Recovering Hurricane Katrina

Attachment of Brick Veneer in High-Wind Regions Hurricane Katrina Recovery Advisory FEMA December 2005 Purpose: To recommend practices for installing brick veneer that will enhance wind resistance in high-wind areas. Key Issues. Brick veneer is frequently blown off Recovering Hurricane Katrina walls of residential and commercial buildings (Figure 1). 

When brick veneer fails, wind-driven water can enter and damage buildings, and building occupants can be vulnerable to injury from windborne debris (particularly if walls are sheathed with plastic foam insulation or Recovering Hurricane Katrina wood fiberboard in lieu of wood panels). Pedestrians in the vicinity of damaged walls can also be vulnerable to injury from falling veneer (Figure 2). 

Figure 1. Failed brick veneer. Plastic foam wall sheathing was Recovering Hurricane Katrina installed over the wood studs (plywood was temporarily installed after the brick failure). Figure 2. The upper portion of the brick veneer at this apartment building collapsed. 

Pedestrian and vehicular traffic in the vicinity of the damaged wall were vulnerable to injury and Recovering Hurricane Katrina damage if remaining portions of the wall were to collapse during subsequent storms. 

Common failure modes include tie (anchor) fastener pull-out (Figure 3), failure of masons to embed ties into the mortar (Figure 4), poor bonding between ties and Recovering Hurricane Katrina mortar and mortar of poor quality (Figure 5), and tie corrosion (Figure 6). Figure 3. This tie remained embedded in the mortar joint while the smooth-shank nail pulled from the stud. 

These four ties were never embedded into the mortar joint. Figure 5. This tie was embedded in the mortar, but the bond was poor. Figure 6. There were several ties in this portion of the wall, Recovering Hurricane Katrina but they failed due to severe corrosion. Ties are often installed before brick laying begins. When this is done, ties are often improperly placed above or below the mortar joints. 

When misaligned, the ties must be angled up or down in order for the ties to be embedded into the mortar joints (Figure 7). Misalignment not only reduces embedment depth but also reduces the effectiveness of the ties because Recovering Hurricane Katrina wind forces do not act parallel to the ties themselves. Figure 7. Misalignment of the tie reduces the embedment and promotes veneer failure. 

Corrugated ties typically used in residential veneer construction provide little resistance to compressive loads. Use of compression struts would likely be beneficial, Recovering Hurricane Katrina but off-the-shelf devices do not currently exist. Two-piece adjustable ties (Figure 8) provide significantly greater compressive strength than corrugated ties. 

Figure 8. Examples of two-piece adjustable ties, one showing base and vee anchor and the other showing eye and Recovering Hurricane Katrina pintle anchor Many buildings that exhibited damaged veneer were not in compliance with current building codes. Building code requirements for brick veneer have changed over the years. 

Model codes prior to 1995 permitted brick veneer in any location, Recovering Hurricane Katrina with no wind speed restrictions. Wall area per tie in some model codes was greater than the current maximum. 

The current masonry code referenced in model building codes, Building Code Requirements for Masonry Structures, ACI 530/ASCE 5/TMS 402 (ACI 530) addresses brick veneer in two manners: Recovering Hurricane Katrina rational design and prescriptive requirements. Essentially all brick veneer in residential and low-rise construction follows the prescriptive requirements. 

The first edition of American Concrete Institute’s (ACI’s) 530 limited the use of prescriptive design to areas with a basic wind speed of 110 mph or less. The 2005 edition of ACI 530 extended the prescriptive requirements to include a basic wind speed of 130 mph, Recovering Hurricane Katrina with lower area per tie limits. 

In locations with a basic wind speed above 130 mph, the rational design approach must be used. Compliance with ACI 530-05 should reduce wind damage. The following Brick Industry Association (BIA) Technical Notes Recovering Hurricane Katrina provide guidance on brick veneer: Technical Notes 28 – Anchored Brick Veneer, Wood Frame Construction, Technical Notes.

Brick Veneer/Steel Stud Walls, and Technical Notes 44B – Wall Ties (available online at www.bia.org). These Technical Notes provide attachment recommendations, Recovering Hurricane Katrina but the recommendations are not specific for high-wind regions and are, therefore, inadequate. Construction Guidance The brick veneer wall system is complex in its behavior. 

There are limited test data on which to draw. The following guidance is based on professional judgment, wind loads specified in ASCE 7-02 "Design Loads for Buildings and Recovering Hurricane Katrina Other Structures,” fastener strengths specified in the American Forest and Paper Association’s (AF&PA’s) National Design Specification for Wood Construction, and brick veneer standards contained in ACI 530-05. 

In addition to the general guidance given in BIA Technical Notes 28 and 28B, the following are recommended: Note: In areas that are also susceptible to high seismic loads, brick veneer should be evaluated by an engineer to ensure it can resist seismic and Recovering Hurricane Katrina wind design loads. Stud Spacing: For new construction, space studs 16" on center, so that ties can be anchored at this spacing. 

Tie Fasteners: Ring-shank nails are recommended in lieu of smooth-shank nails. A minimum embedment of 2" is suggested. Ties: For use with wood studs: two-piece adjustable ties are recommended. However, Recovering Hurricane Katrina where corrugated steel ties are used, use 22-gauge minimum, 7/8" wide by 6" long, complying with ASTM A 366 with a zinc coating complying with ASTM.

A 153 Class B2. For ties for use with steel studs, see BIA "Technical Notes 28B – Brick Veneer/Steel Stud Walls.” Stainless steel ties should be used in areas within 3,000 feet of the coast. Tie Installation Install ties as the brick is laid so that the ties are properly aligned with Recovering Hurricane Katrina the mortar joints. Install brick ties spaced per Table 1. 

Studs should be installed at 16" spacing. Veneer tie locations for 24" stud spacing are included for repairing damaged veneer on existing buildings with the wider stud spacing. Locate ties within 8" of door and Recovering Hurricane Katrina window openings and within 12" of the top of veneer sections. Bend the ties at a 90-degree angle at the nail head in order to minimize tie flexing when the ties are loaded in tension or compression (Figure 9). Figure 9. 

Bend ties at nail heads Embed ties in joints so that mortar completely encapsulates the ties. Embed a minimum of 1.5" into the bed joint, Recovering Hurricane Katrina with a minimum mortar cover of 5/8" to the outside face of the wall (Figure 10). Figure 10. Tie embedment [Begin table]

Animals Gnawing On The House

It seems like there isn't any part of your house that animals won't chew on, seems that they like siding and they’ll chew on the lead vent stack covers. So how can we keep this chewing and other forms of animal damage from happening. Squirrels for example must gnaw and must gnaw a lot to  read more..

Radon Testing

Heat Recovery Ventilation (HRV) systems shall not be installed in rooms that contain friable asbestos. 14.8.4 In HRV installations, supply and exhaust ports in the interior shall be located a minimum of 12 feet apart. The exterior supply and exhaust ports shall be positioned to avoid blockage by sno  read more..

Clean Up After A Flood

Then appropriate, replace lood damaged windows with

vinyl or metal framed windows. Hollow core or polystyrene foam illed metal doors are water resistant. Metal in

both windows and doors may rust slightly but that is easily

repaired. Marine plywo  read more..

Dehumidify A Flooded Home Without A Dehumidifier

As illustrated in Figure 1, the evaporator (c) and the condenser (e) are the most critical components and dominate the system performance. The evaporator is fitted with a porous tower-packing material, in this case HD Q-PAC® structured media (Lantec Products, Inc., Agoura Hills, CA), Dehumidification Dehumidify A Flooded Home Without A Dehumidifier&n  read more..

Earthquake Cleanup

These debris removal activities, which have important financial allegations, that could happen in a stressful period when search and rescue operations are under way and the city is struggling to provide typical services to the people. Key Debris Removal Earthquake Cleanup of events in the beginning phase include, arrange  read more..

Floodplain

How are communities involved in the Flood Damage Floodplain Insurance Study process? Prior to engaging community officials, FEMA coordinates with other Federal agencies (e.g., U.S. Corps of Engineers) to identify and gather existing data that may inform FIS development. 

FEMA then hold  read more..

Pipe Leaks

Water Damage Pipe Leaks could be called the silent destroyer, there might be a water leak for days that goes unnoticed then squish you step into it with your stocking feet. But, you think, where did it come from, it’s fairly close to the kitchen sink. You open the cabinet and pull everything out from insid  read more..

Styles Of Security Fences

Each year, people in this country are killed or seriously injured by all types of extreme weather, despite advance warning. In 2012, there were more than 450 fatalities and nearly 2,600 injuries due to extreme weather, like tornadoes, hurricanes, floods, extreme heat, and wildfires. NOAA's Weather-R  read more..

Health Effects Caused By Lead Poisoning

Health effects caused by lead exposure can be subdivided into five developmental stages: Normal, physiological changes of uncertain significance, pathophysiological changes, overt symptoms (morbidity), and mortality. Within this process there are no sharp distinctions, butrather a continuum [ME  read more..

Crawlspace Drying

Some homes have more than one type of foundation design. For example, it is very common to have both a basement under part of the house and then to have a slab-on-grade or crawl space under the other part of the house. In these circumstances a mixture of Radon Mitigation Crawlspace Drying reduction methods might be requir  read more..